HomeMy WebLinkAboutchange order 1 (2) •
Al11
June 1, 1999
CHANGE ORDER NO. 1
To : Ron Cox
City Manager
From: Mickiel Hodge
Community Development Director
SUBJECT: 12 Inch Water Line Relocation at Friendswood High School
CONTRACTOR: David Wight Construction Co., Inc.
CONTRACT DATE: December 7, 1998
ORIGINAL CONTRACT AMOUNT: $23,375.00
The Above contract has been increased by the following amount:
Additional materials and work were required to repair the existing 16 inch water line. Existing plans
showed a 12 inch water line exiting Water Well#5. In the field, it was discovered that the existing water
line at Water Well#5 is a 16 inch water line. Additional fittings were required, in order to connect the
existing 16 inch water line with the relocated 12 inch water line.
SUMMARY
•
Original Contract Amount: $23,375.00
Change Order No. 1, Add: $ 4,546.80
Change in Contract Time, Add: none
Amend Contract Amount: $27,921.80
RECOMMENDED FOR APPROVAL:
• • 14/- /9-
Date: 6�! `7 9
APPROVED:
City of Friendswood
By: __2V7?-44,-Gi
f .,
Date: