HomeMy WebLinkAboutchange order 1 (2) • Al11 June 1, 1999 CHANGE ORDER NO. 1 To : Ron Cox City Manager From: Mickiel Hodge Community Development Director SUBJECT: 12 Inch Water Line Relocation at Friendswood High School CONTRACTOR: David Wight Construction Co., Inc. CONTRACT DATE: December 7, 1998 ORIGINAL CONTRACT AMOUNT: $23,375.00 The Above contract has been increased by the following amount: Additional materials and work were required to repair the existing 16 inch water line. Existing plans showed a 12 inch water line exiting Water Well#5. In the field, it was discovered that the existing water line at Water Well#5 is a 16 inch water line. Additional fittings were required, in order to connect the existing 16 inch water line with the relocated 12 inch water line. SUMMARY • Original Contract Amount: $23,375.00 Change Order No. 1, Add: $ 4,546.80 Change in Contract Time, Add: none Amend Contract Amount: $27,921.80 RECOMMENDED FOR APPROVAL: • • 14/- /9- Date: 6�! `7 9 APPROVED: City of Friendswood By: __2V7?-44,-Gi f ., Date: